The intervention, agreed upon with residents and in collaboration with the Ayuntamiento de Tacoronte, focuses on the insular roads TF-165 and TF-163. The objective is to enhance the collection, conduction, and evacuation of water from the slopes and agricultural land.
The works address existing drainage problems in the area, which became particularly evident during Storm Therese between March 18 and 26, 2026, causing overflows, blockages, and localized flooding in El Pris.
The actions, carried out in phases, include the construction of a new open channel two meters wide and 1.70 meters high, and a stepped channel approximately three meters wide and two meters high. In a second phase, planned for January 2027, a 1,500 mm diameter collector and a 630 mm pipe will be built.
Additionally, the evacuation system towards the ravine will be improved with a new 1,500 mm diameter pipe, doubling the drainage capacity at this point. An energy dissipation area will also be conditioned to reduce water speed and promote controlled evacuation during intense rainfall.
The overall works will renew drainage infrastructure, improve rainwater collection and conduction capacity, and reduce impacts on the road network and urbanized areas downstream.